Which report provides a comparison of planned versus actual costs in GFEBS?

Study for the GFEBS Project Systems Exam. Use flashcards and multiple choice questions, complete with explanations. Get ready to excel in your exam!

The report titled S_ALR_87013532 - Plan/Actual/Variance is specifically designed to facilitate a comparison of planned costs versus actual costs within the GFEBS (General Fund Enterprise Business System). This report enables users to analyze budgeted amounts against the expenditures incurred, providing valuable insight into how well a project or initiative is performing in relation to its financial plan.

By using this report, project managers and financial analysts can easily identify variances, which can help in making informed decisions about resource allocation, adjusting budgets, and addressing any discrepancies between the planned budget and actual spending. The ability to visualize these comparisons is crucial for effective project management and financial oversight.

Other reports might provide useful data, but they do not specifically focus on the planned versus actual cost comparison in the same manner or depth as this particular report does. This specificity makes S_ALR_87013532 an essential tool in the GFEBS framework for effective cost management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy